Computer Engineering and Applications ›› 2016, Vol. 52 ›› Issue (20): 227-230.

Previous Articles     Next Articles

Predicting model of fuzzy linear programming with fuzzy variables in capacity allocation of mine

SHAO Liangshan1, LI Yongli1, ZHAO Linlin1, WEN Tingxin2, KONG Xiangbo2   

  1. 1.Institute of System Engineering, Liaoning Technical University, Huludao, Liaoning 125000, China
    2.School of Business Administration, Liaoning Technical University, Huludao, Liaoning 125000, China
  • Online:2016-10-15 Published:2016-10-14

矿山产能分配的变量模糊线性规划模型

邵良杉1,李永利1,赵琳琳1,温廷新2,孔祥博2   

  1. 1.辽宁工程技术大学 系统工程研究所,辽宁 葫芦岛 125000
    2.辽宁工程技术大学 工商管理学院,辽宁 葫芦岛 125000

Abstract: For the sake of dealing the problem of the fuzzy allocation during mining, a fuzzy linear programming model with fuzzy variables is developed based on fuzzy structured element. The mine capacity is analysed and the comparison among fuzzy numbers is transformed into the comparison among monotonic functions, the fuzzy linear programming model with fuzzy variables is transformed into a classical linear programming by using structured element order. A mine as a case study is analysed. The results show that fuzzy problems are analysed exactly in a actual problem, and the resolution is simplified. The fuzzy allocation is obtained with the most fuzzy profit. The new method is better than the method based on the structured element order.

Key words: mine, productivity, fuzzy variable, possibilistic linear programming, structured element

摘要: 针对矿山资源开采过程中产能不确定的分配问题,引入了模糊结构元素理论。将产能用结构元表示,并利用结构元加权序将模糊数比较转化为单调函数比较,将含有模糊变量的线性规划问题等价转化为经典线性规划问题。以某矿山为例,建立矿山产能分配的变量模糊线性规划模型,并进行求解。结果表明:实现了将实际问题中的模糊事件进行精确表达,原问题的求解更简便。得到矿山产能取得最大可能利润时的可能分配。应用结构元加权序求解的线性规划模型优于结构元元序的。

关键词: 矿山, 产能, 模糊变量, 可能性线性规划, 结构元